Drax, one of the UK’s largest electricity generators, has signed an agreement with Brookfield and Radiant to build an AI data center at the Drax power station in North Yorkshire. Announced on November 3, 2026, the plan targets more than 1 GW of compute capacity across three phases. According to Brookfield’s estimate, total investment, including semiconductor chips, could exceed £20 billion. Of that, £2.5 billion will be spent in the first phase.
Existing plant infrastructure at the heart of the plan
The project isn’t being built on a greenfield site; it’s being built on the plant’s current infrastructure. The site has more than 400 hectares of land, about 4 GW of grid access, 2.6 GW of active and dispatchable generation capacity, and cooling systems. Proximity to the UK fiber network also completes the other condition required for large-scale compute.
The first phase targets up to 100 MW of compute capacity, and commercial operations are expected to begin in Q1 2028. In this phase, electricity will be drawn directly from the grid, with Drax managing supply.
The power model changes in the second phase
The second phase, covering 2028-2031, aims to add 500 MW of capacity. This time, electricity will come directly from the plant’s own generation through a long-term power purchase agreement. This model, described as behind-the-meter, depends on obtaining the necessary permits. The third phase, after 2031, envisions additional capacity using the same approach.
This phased structure keeps the initial investment as a grid-connected development while moving the plant’s existing generation to the center of the project. In other words, the project isn’t a data center built next to a power plant; it’s designed as a compute campus that grows with the plant’s power.
Construction depends on customers and approvals
Radiant, Brookfield’s UK-based AI infrastructure platform, will manage design, customer discussions, and commercialization. The company is looking for anchor customer commitments before construction begins. Land, power integration, and planning processes remain with Drax.
The first phase is not yet finalized. It requires planning permission, regulatory and grid approvals from the government and relevant bodies, an acceptable tenant, commercial agreements, and the parties’ final investment decision. A planning application is being prepared; public consultation is expected to begin in November 2026. The partners also plan to set up a voluntary community benefit fund for communities around the site.
In the announcement, Radiant CEO Mahdi Yahya said the project would provide “British researchers, startups and companies with access to leading-edge compute power in their own country”.
Biomass contract and financing side
The later phases intersect with Drax’s existing biomass arrangements. The company had signed a Contract for Difference with the UK government in November 2025 covering about 6 TWh of biomass generation per year between April 2027 and March 2031. This contract allows it to request that up to 500 MW of capacity during the period be allocated for data center use. Such use would require an agreement with the government and the Low Carbon Contracts Company; cost-effectiveness for consumers, energy security, and sustainability will also be assessed.
Investment capital and operating capability will be provided through the AI infrastructure joint venture between Brookfield and Qai. The pair had announced a $20 billion joint venture on December 9, 2025 to invest in AI infrastructure in Qatar and selected international markets. Qai is a subsidiary of the Qatar Investment Authority.
The deal combines a ready-made energy site with a dedicated AI development platform and an existing investment vehicle. The real test of the plan is execution: finding a tenant for the first phase, completing approvals, and reaching a final investment decision. The larger build will have to align with Drax’s generation commitments and obtain the necessary permits.
Source: Unite.AI